Hangzhou 8.20MWh user-end industrial and commercial energy storage project

Hangzhou 8.20MWh user-end industrial and commercial energy storage project

Project Overview: The project is located in Hangzhou, Zhejiang Province. The total installed capacity is 8.20MWh. The total investment in the project is approximately 14 million.
It adopts peak and valley arbitrage and electricity discount models.
Installation Capacity: 8.20MWh
Annual Charge And Discharge Capacity: About 4.5 million kilowatt hours of electricity
Owner's Income: Saving customers more than 1 million yuan in electricity bills every year.
Investment Recovery Period: Saving customers more than 1 million yuan in electricity bills every year.
Investment Recovery Period: 3.50 years
Project Proposals: Lei Shing Hong Energy provides comprehensive solutions and products for the project (including 22 sets of standard 372kWh liquid-cooled energy storage outdoor cabinets + 2 sets of main control cabinets + AC side converter and boost integrated cabin+ 2 energy storage grid-connected cabinet + a complete set of EMS and cloud platform surveillance system.

case